Georgia Lien Waiver Requirements
Georgia requires lien waivers to follow the statutory form, and a waiver becomes binding after 90 days unless an affidavit of nonpayment is filed. WaiverPilotPRO generates print-ready Georgia waivers for free.
Does Georgia require a specific lien waiver form?
Yes — a statutory lien waiver form is required.
Georgia waivers must follow the statutory form and become binding after 90 days unless an affidavit of nonpayment is filed. Track your waivers carefully to protect your rights.
The 4 lien waiver types in Georgia
Conditional Progress
Waives lien rights for a progress payment, only once that payment is actually received.
Unconditional Progress
Waives lien rights for a progress payment that has already cleared — use only after funds arrive.
Conditional Final
Waives all remaining lien rights upon final payment, conditioned on receipt of that payment.
Unconditional Final
Releases all lien rights after final payment has cleared — the strongest release.
Notarization
Not required. Georgia does not require lien waivers to be notarized.
Generate a free Georgia lien waiver form (PDF & Word)
Create a print-ready Georgia conditional, unconditional, or final waiver in minutes and download it as a PDF or Word document — no account required.
Georgia lien waiver FAQ
Does Georgia require a specific lien waiver form?
Yes. Georgia waivers must follow the statutory form to be valid.
What is the Georgia 90-day waiver rule?
In Georgia, a lien waiver becomes binding after 90 days unless an affidavit of nonpayment is filed within that window.
Lien waiver requirements by state
This page is general information, not legal advice. Lien waiver rules change — confirm current requirements with a construction attorney or your state statute before relying on a waiver.